Rural Electrification Tanzania
This website displays open data about Swedish aid, which shows when, to whom and for what purpose Swedish aid is paid out, as well as what results it has produced. This page contains information about one of the contributions financed with Swedish aid.
All activities related to the contribution are shown here. Click on an individual activity to see in-depth information.
Total aid 599,119,431 SEK distributed on 0 activities
A list of all paid transactions for a specific contribution is presented here. Each payment can be traced to a specific activity. Negative amounts indicate that there has been a refund.
0 transactions
No transactions available for this contribution
0 contribution documents
Link to download |
---|
No contribution documents available for this contribution
Result
During the period under review, the Agency received a total of TZS 247.99 billion from Development Partners which was used to finance rural energy projects. As of the reporting period, a total of 10,435 villages out of 12,318 villages (GN of 2018), equivalent to 84.7% are connected to electricity by extending the infrastructure to the village headquarters. During the period under review 1,796 villages were electrified. It should be noted during the reporting period Sweden did not disburse to REA, but REA was using funds for ongoing project activities which was disbursed during the previous year. The report covers progress of projects implemented under the support of Development Partners (DPs) and the performance of the Rural Energy Fund (REF) in provision of modern energy services in the rural areas of Mainland Tanzania. Some of the key milestones achieved during the period include electrification of 45 villages out planned 65 under the Turnkey Phase III Round I project, electrification of 1,751 villages out of 2,157 planned for 2022/23 under Turnkey Phase III Round II, completion of structural works of 1x 20MVA, 220/33 kV Substation in Ifakara and extension of distribution line in Kilombero and Ulanga Districts. Under Result Based Financing, 399 households were connected which lead to connection of 17,302 out of 20,020 initial customers which is equivalent to 86.42%. The RBF is 100% funded by Sweden. Further, through the DPs initiatives, the BTIP VEI achieved connection of 8,617 cumulatively a total of 32,628 out of 35,391 initial customers were connected equivalent to 92%. The project electrified 115 electrified and six (6) hamlets. Initiatives are ongoing to electrify rural health and water facilities to prevent spread of infectious diseases including COVID19 whereby 229 out of 403 facilities equivalents to 50% were electrified. Contractors for Densification IIB have completed site mobilization, detailed survey and design & drawings have been completed, funded by Sweden and Norway. Furthermore, 200 hamlets were electrified through REDP 2A during the period under review and 71,639 customers were connected. Cumulatively, a total of 1,065 out of 1,265 have been electrified and 73,557 customers have been connected equivalent to 71.3% increase, funded by Sweden, Norway and EU. Initiatives under the Peri Urban are also going on to ensure those areas are electrified according. A total of 127 villages electrified equivalent to increase of 76.97 percent. Cumulatively a total of 165 villages electrified, which is 100% and 11,860 customers connected, cumulatively makes a total of 13,418 out of 16,707 initial customers equivalent to 80.3% were connected. The Agency received UNQUALIFIED OPINION for fiscal year 2022/23 from the audited conducted by Controller and Auditor General. According to the Annual Progress Report, the Agency will continue to perform its obligations to ensure there is a good value for money and the intended results is achieved.
The objective with this rural elecrification programme is to electrify large areas of rural Tanzania that have to date not been electrified. This will be achieved both with grid extension projects and with offgrid electrification, e.g. isolated so called minigrids. There will also be densification projects, adding more customers to already electrified rural areas. Electrification is just a means to an end. It will enable e.g. households to light up for children to study better, for charging of phones, watching TV etc. It will also enable smallscale businesses to develop, rural schools to light up, medical clinics to store medicine and provide safer birth deliveries. Generelly, electrification is one of the key enablers for development. The development objective of Tanzania's Rural Energy Agency (REA) and its Rural Energy Fund (REF) is socio-economic development and poverty alleviation in rural Tanzania through the provision of increased access to modern energy services. The overall objective of the Swedish support to REA and the REF is to contribute to reliable and sustainable energy access for poor people with low climate impact, as well as increased procurement transparency and regulatory improvements that strengthens private sector investments in renewable energy.
Swedish aid in numbers and reports
Do you want to read more about the results of Swedish aid?